GATE 1 Offer and Review session + Check List

Welcome to Review and Offer Day!

This is pre-check list for reviewers and teams.

We will start at Friday 21.2.2025 at 14:00 on ZOOM-channel. Link will be shared before session!

About review process

  • The feasible checkpoints are mentioned below as a check list. We would review five selectd points are randomly
  • The review is conducted by the Mentors, instructor or selected externals
  • Group should be able to shoe several evidences and artifacts about project planning before review.

Primary target for review

Make sure your team is capable and ready for implementation phase.

  • Team status and visibility
  • Clear Purpose of the Pproject
  • Project planend with schedule and resources
  • Documented Requirement Specification + Epic/Feature Roadmap
  • AND MOST IMPORTANT Your team's offer What a customer can get and how much it costs?

Agenda for review session

  • We will start 14:00 and session last at minimum 15:00
  • There will will three to five (3-5) teams selected by randomly for Review process

  • Selected Team give short introduction by team leader and team members (2 min)

  • It could be valuable to have PowerPoint Set about your team + project?! Please make sure you have one!
  • Tell about your project target and schedules + resources
  • Show case of Features which they will deliver (3 min)
  • Possible Roadmap for selected epics/features (1 min)
  • Show you cost estimation (1 min)
  • Price Tag to whole projet (1 min)

Mentors will ask some questions and then discussion 2-4 min

Keep in mind!

  • BEWARE TO BE ABLE INTRODUCE YOUR TEAM!
  • Activate use of WebCam during the review session, so all members are visible!
  • Offical offer proposal should be updated before 13:00
  • **Your team has to update team specific Offer Proposal template accroding your own. Link features with your proposal
  • Check that the documentation does not do not contain misleadin "template" garbage. Documents should be appropriate and can be presented to e.g. an outside person.
  • Make sure you all material easy to be share.
  • You can speak Finnish, but by default session in English

Artefacts under review

Important documents to be reviewed

  • Team introduction/Web Page
  • Current Status
  • Offer to the customer
  • Project plan/communication/risks in order
  • Requirement Specification
  • Feature Roadmap
  • Mockup for som selected features - If you are planning to implement new features in some cases it would be nice to show a mockup to customer
  • Budget for whole project - linked as EXCEL
  • Short Web Page/PowerPoint as team introduction

Official Checkpoints for G1 Offer & review

Check point id Description Status
CheckPoint01 The group's introduction can be found on the home pages or OPF ?
CheckPoint02 Recording of Work hours in use and up-to-date ?
CheckPoint03 Project schedules updated in the project plan? ?
CheckPoint04 Feature specific User Stories are evaluated by the team !!!This is done after review!!!
CheckPoint05 Project stages (G0-G5) recorded and linked as Gantt or EPIC ROADMAP chart can be found in the project plan ?
CheckPoint06 Preresourcing / division of tasks: the project plan shows a rough division of roles ?
CheckPoint07 The workload estimate can be found in the project plan ?
CheckPoint08 Linking between documentation/material is working without problems ?
CheckPoint09 Epic "roadmap" defined. In which order the features are going to be released ?
CheckPoint10 Some preliminary Test Cases defined for features and documented as issues or Acceptance criterias on feature pages ?
CheckPoint11 Initial feature prioritization. Which features are made first? Why? ?
CheckPoint12 Stakeholders information documented? Who is a client? Who is a end users? etc.. ?
CheckPoint13 End User target group profiled, for whom the product is made (can be found in the specification of requirements) ?
CheckPoint14 The group has an offer to the customer. The hourly prices has been according the catalog ?
CheckPoint15 Link to the risk management plan can be found from the project plan (and updated) ?
CheckPoint16 Link to the communication plan can be found from the the project plan (and updated) ?
CheckPoint17 Link to the requirement specification document can be found from the project plan (and updated) ?
CheckPoint18 Roles, actors and stakeholders described in requirement specification ?
CheckPoint19 Main features of the product described in requirement specification (MindMap eg.) ?
CheckPoint20 User interface example as Mockups defined and will be able to open by the customer without extra authentiation ?
CheckPoint21 In the requirements specification you can find links to the mock implementation or embended images ?
CheckPoint22 The project agreement/contract updated (OPTIONAL) NOT NEEDED
CheckPoint23 An A4 printout of the project contract is easily available NOT NEEDED
CheckPoint24 The risk management plan can be found as part of the project plan (the link to the page also works) ?
CheckPoint25 The communication plan can be found in the project plan (the link to the page also works) ?
CheckPoint26 Non Functional - Security requirements defined and documented in requirement specification ?
CheckPoint27 Roles, actors and stakeholders defined and described ?
CheckPoint28 - -
CheckPoint29 Release plan for product features visualized as Gitlab "Roadmap"-view ?
CheckPoint30 User interface examples / demo environment. In the requirements specification you can find links to the mock implementation ?
CheckPoint31 The project agreement can be found ?
CheckPoint32 Selected Features are documented in requirement specification as own pages ?
CheckPoint33 Product Mindmap updated ?
CheckPoint34 Roles documented, who does what and when? ?
CheckPoint35 There is updated risk management list? ?
CheckPoint36 Team has identified risks (10-20) ?
CheckPoint37 The Feature Roadmap is known by all members ?
CheckPoint37 If some risk occurs, will it be clear who/what will happen then --> Let's check risk management ?
CheckPoint38 Rough outline of the required system architecure/database/data warehouse solution in requirement spefication ?
CheckPoint39 Selected technology choices recorded (in requirements specification or architecture description) ?
CheckPoint40 The Budjet proposal for Sprints 03-07 What does this cost to customer? Includes also Excel-file to show calculation ?
CheckPoint41 Master Test Plan Updated for project ?
CheckPoint42 Test Case ideas documented in feature descriptions ?

General process before G1

Each teams are going through multiple pahts. Team members are assigned for certain tasks which are needed to execute before planning phase is over.

uml diagram